Presented By CANAAN REALTY

Building the
Future of Semiconductors

Tracking Micron’s $100B investment in Clay, NY. Live updates on construction and local impact.

Phase 1 Progress 0%

Last update: March 25, 2026

$100B
Total Investment
$17B
Yearly Impact
9,000+
New Jobs
2045
Full Capacity

Construction Roadmap

In Progress

Site Clearing & Grading

Mass grading and staging of heavy equipment across the 1,400-acre site.

Jan – Jun 2026
45%
Upcoming

Foundation Work

Deep foundation systems and concrete pouring for primary structures.

Starts Q2 2026

Progress Logs

Latest Report

Fab 1 Excavation & Utility Upgrades

  • Excavation intensified for the first fabrication building (Fab 1), moving thousands of cubic yards daily.
  • Coordination with National Grid for high-voltage substation upgrades to provide industrial capacity.

Mass Grading Phase

Contractor Gilbane established primary on-site construction offices and logistics hubs. Workforce training initiatives were solidified with local technical colleges.

Historic Groundbreaking

Official groundbreaking ceremony held January 16, 2026. Preliminary perimeter fencing and environmental sensors installed across the White Pine park boundaries.